MBSDMP Project Status


Figure 1: Overall Work Schedule and Progress as of September 2019


The Progress Report No. 20 accounts the activities and accomplishments for the month of September 2019 under the Operational Phase of the Project. The key activities and milestones during the reporting period were the: (1) MBSDMP Thematic Meetings (2) Updating the Final Master Plan Report (3) Updating the ICZM Planning Framework (4) Supporting Activity – Spatial Planning Training

Full report could be accessed on the link below

The Progress Report No. 20 - September 2019 

The Progress Report No. 19 accounts the activities and accomplishments for the month of August 2019 under the Operational Phase of the Project. The key activities and milestones during the reporting period were the: (1) Enhancing the Integrated Coastal Zone Management (ICZM) Planning Framework (2) Consultation Workshops (3) Innovative Financing Meeting (4) Development of the 2nd Audio Visual Presentation (AVP) (5) Updating the Final Master Plan Report (6) Supporting Activities – WQMA Consultation Workshop and Master Plan and Feasibility study of Urban Drainage and Flood Control


Full report could be accessed on the link below

The Progress Report No. 19 - August 2019 

The Progress Report No. 18 accounts the activities and accomplishments for the month of July 2019 under the Operational Phase of the Project. The key activities and milestones during the reporting period were the: (1) Enhancing the Integrated Coastal Zone Management (ICZM) Planning Framework (2) Consultation Workshops for the Operational Planning Phase of the Master Plan (3) Investment and Financial Planning Week  (4) Updating the Final Master Plan Report (5) Development of IEC Materials and Awareness Raising Campaigns (6) Supporting Activities – Presentation of the Master Plan report to various National Government Agencies’ Events.


Full report could be accessed on the link below

The Progress Report No. 18 - July 2019


The Progress Report No. 17 accounts the activities and accomplishments for the month of June 2019 under the Operational Phase of the Project. The key activities and milestones during the reporting period were the: (1) Stakeholder engagements to fine tune the Masterplan (2) Communication Strategy meeting to complement the Master Plan (3)  Developing the Integrated Coastal Zone Management (ICZM) Planning Framework of Manila Bay Coastal Waters (4)  Supporting activities – Participation to various events relating to the rehabilitation of Manila Bay, and Coordination Meeting to NEDA and other National Government Agencies (NGAs)

Full report could be accessed on the link below

The Progress Report No. 17 - June 2019 


•  The Progress Report No. 16 accounts the activities and accomplishments for the month of May 2019 under the Final Master Plan Phase of the Project. The key activities and milestones during the reporting period were the: (1) Packaging and Submission of the Final Master Plan Report (2) MBSDMP Team Meeting (3)  MBSDMP Communication Strategy Plan Meetings (4) Zoning Framework Meeting (5) 5th and 6th Technical Committee Meetings (6) Supporting Activities - Photovoice Presentation and Netherland Learning Visit

Full report could be accessed on the link below

The Progress Report No. 16 - May 2019 


•  The Progress Report No. 15 accounts the activities and accomplishments for the month of April 2019 under the Final Master Plan Phase of the Project. The key activities and milestones during the reporting period were the: (1) Packaging and Submission of the Final Draft Master Plan, Institutional Set Up, and Capacity Building Report (2) MBSDMP Meetings and Small Stakeholder workshop for the refinement of the Final Master Plan Report (3) Supporting Activities – Spatial Modelling Training

Full report could be accessed on the link below

The Progress Report No. 15 - April 2019

The Progress Report No. 14 accounts the activities and accomplishments for the month of March 2019 under the Final Draft Master Plan Phase of the Project. The key activities and milestones during the reporting period were the: (1) Submission of the Strategy Building Report (2) Regional Stakeholder Consultations – Region III, IVA, NCR, CSOs, Private Sector and NGAs (3) Technical Committee Meeting – Strategy Building Phase and the (4) Designing of the Final Draft Masterplan and Institutional Set-Up Report.

Full report could be accessed on the link below

The Progress Report No. 14 - March 2019


The Progress Report No. 13 accounts the activities and accomplishments for the month of February 2019 under the Strategy Building Phase of the Project. The key activities and milestones during the month of February 2019 were series of Strategy Building Workshops, Stakeholder Consultations for Region III, IVA, NCR and NGAs, and a supporting activity of Spatial Modelling Training.

Full report could be accessed on the link below

The Progress Report No. 13 - February 2019


The Progress Report No. 12 accounts the activities and accomplishments for the month of January 2019 under the Strategy Building Phase of the Project. The key activities and milestones during the month of January 2019 were: (1) Data Gathering Activities in various LGUs in the Manila Bay Area; (2) 1st Strategy Building Team Workshop; (3) Series of Focal Theme Cluster Meetings for Strategy Building Stage; (4) Institutional Set Up Meeting; (5) Development of the Modelling Framework for Manila Bay Area; (6) DENR Manila Bay Rehabilitation Meeting and (7) Supporting Activities that include Manila Bay Rehabilitation Launch and NEDA Meeting.

Full report could be accessed on the link below

The Progress Report No. 12 - January 2019


The Progress Report No. 11 accounts the activities and accomplishments for the month of December 2018 under the Strategy Building Phase of the Project. The key activities and milestones during the month of December 2018 were: (1) Technical Committee (TC) Meeting (2) Preparatory Activities for the LCF Workshop (3) Modeling of Manila Bay Area with Key Indicators and (4) Data Gathering Activities in various LGUs in the Manila Bay Area and NGAs concerned.

Full report could be accessed on the link below

The Progress Report No. 11 - December 2018


The Progress Report No. 10 accounts the activities and accomplishments for the month of November 2018 under the Strategy Building Phase of the Project. The key activities and milestones during the month of November 2018 were: (1) Series of CMER (Netherlands Commission for Environmental Assessment) Meetings with NGAs; (2) Data Gathering Activities with various LGUs in the Manila Bay Area; (3) Series of Focal theme meetings for the Manila Bay’s Potential Goal and Indicators and (4) Compliance of Technical committee’s comment on Focal theme reports and Situational Analysis Atlas

Full report could be accessed on the link below

The Progress Report No. 10 - November 2018


The Progress Report No. 9 accounts the activities and accomplishments for the month of October 2018 under the Strategy Building Phase of the Project. The key activities and milestones during the month of October 2018 were: (1) MBSDMP Strategic Meeting for the next phase of the project; (2) Review of Manila Bay’s Goal and Identification of Indicators per Focal Theme and (3) Supporting Activities that include Manila Bay Rehabilitation Launch and NEDA Meeting.

Full report could be accessed on the link below

The Progress Report No. 9 - October 2018


The Progress Report No. 8 accounts the activities and accomplishments for the month of September 2018 under the Situational Analysis Phase of the Project. The key activities and milestones during the month of September 2018 were: (1) Preparation, Packaging and Submission of the Situation Analysis and Focal theme report and (2) Technical working group presentation of focal theme reports (Disaster Risk Reduction and Climate Change Adaptation (DRR-CCA), Upgrading Informal Settlement, Water Quality Improvement, Ecosystem protection, and Inclusive Growth). The MBSDMP team also transferred their operations to their new office location at Antel Building in Ortigas Center, Pasig City, Metro Manila.

Full report could be accessed on the link below

The Progress Report No. 8 - September 2018


• The Progress Report No. 7 accounts the activities and accomplishments for the month of August 2018 under the Situational Analysis Phase of the Project. The key activities and milestones during the month of August 2018 were: (1) Stakeholder Consultation workshops; (2) Secondary Data Collection and Analysis; (3) DET partners engagement with Project stakeholders (4) Drafting the thematic reports and preparing the scorecard framework (5) Preparation of the Situation Analysis Report.

Full report could be accessed on the link below

The Progress Report No. 7 - August 2018


• The Progress Report No. 6 accounts the activities and accomplishments for the month of July 2018 under the Situational Analysis Phase of the Project. The key activities and milestones during the month of July 2018 were: (1) Stakeholder Consultation workshops and Key Informant Interviews (KIIs) (2) Secondary Data Collection and Analysis (3) Primary data collection and analysis (4) Scorecard Framework (5) 2nd Technical Committee Meeting (6) Capacity-building training for NEDA.

Full report could be accessed on the link below

The Progress Report No. 6 - July 2018


• The Progress Report No. 5 accounts the activities and accomplishments for the month of June 2018 under the Situational Analysis Phase of the Project. The key activities and milestones during the month of June 2018 were (1) Acceptance of the Inception Report and Work, and the Financial Plan for MBSDMP (2) Continuation of Situation Analysis Stage, including gathering of available documents and information about Manila Bay (3) Conduct of focus group discussions (FGDs) and workshops with various stakeholders (4) Preparations for July Feedback Week

Full report could be accessed on the link below

The Progress Report No. 5 - June 2018


• The Progress Report No. 4 accounts the activities and accomplishments for the month of May 2018 under the Situational Analysis Phase of the Project. The key activities and milestones during the month of May 2018 were: (1) Acceptance of the Inception Report (2) Commencement of Situation Analysis Stage (3) Gathering of available documents and information about Manila Bay (4) Conduct of focus group discussions (FGDs) with various stakeholders (5) Finalization of the Technical Committee (TC) for the MBSDMP

Full report could be accessed on the link below

The Progress Report No. 4 - May 2018


The Progress Report No. 3 accounts the activities and accomplishments for the month of April 2018 under the Initial Phase of the Project. The key activities and milestones during the month of April 2018 were: (1) Submission of the Inception Report (2) Gathering of available documents and information about Manila Bay as preliminary activities of the Situation Analysis Stage; and (3) Formulation of the Technical Committee (TC) for the MBSDMP.

Full report could be accessed on the link below

The Progress Report No. 3 - April 2018


• The Progress Report No. 2 accounts the activities and accomplishments for the month of March 2018 under the Initial Phase of the Project. The key activities and milestones during the month of March 2018 were: (1) Inception activities including preparation of work schedule toward preparation of the Inception Report; (2) Gathering of available documents and information about Manila Bay as preliminary activities of the Situation Analysis Stage; and (3) Developing the information system for the Project.

Full report could be accessed on the link below

The Progress Report No. 2 - March 2018


• The Progress Report No. 1 accounts the activities and accomplishments for the month of January and February 2018 under the Initial Phase of the Project. The key activities and milestones during period were: (1) Inception Planning Workshop (2) DET-LCF First Meeting (3) Kick Off Meeting (4) Project Guidelines Meeting (5) LCF Workplan Meeting

Full report could be accessed on the link below

The Progress Report No. 1 - January and February 2018

Events

Kick-Off Meeting | February 13, 2018

The MBSDMP Project Kick-off Meeting was held at NEDA Executive Lounge on 13 February 2018. The Kick-off Meeting was presided by Undersecretary Rolando G. Tungpalan and was attended by NEDA INFRACOM staff; representatives from the Dutch Embassy, representatives from OIDCI, TRACT, and UPLBFI; the Dutch Expert Team (DET), and the Local Consultants.

Feedback Week and Technical Committee Meeting cum DET-led Training

A feedback week which was attended by about 20 personnel of NEDA and some identified relevant NGAs were invited for a participatory modelling and the first Technical Committee Meeting which was represented by various stakeholders.

6 Nov 2018 | Presentation of Strategic Environmental Assessment (SEA) by CMER/NCEA

The group from CMER/Netherlands Commission for Environmental Assessment (NCEA) introduced the Strategic Environmental Assessment (SEA), and its integration to the MBSDMP.

National Fisherfolk Day | May 31, 2018

The National Fisherfolk Day was organized by the Pangisda-Pilipinas and was represented by groups of fishermen families together with the MBSDMP Study Team. It was held last May 31, 2018 at the Philippine Rural Reconstruction Movement.

26 Sept 2018 Technical Committee Meeting

The Technical Committee (TC) meeting held last 26 September 2018 at Hotel Rembrant in Quezon City was attended by various stakeholders of the project.

25-26, 29-30 Apr 2019 | Spatial Modelling Training

A Spatial Modelling Training was conducted by Deltares to teach representatives from government agencies in utilizing data, simulating scenarios and projections, and generating visual tools for better appreciation and decision-making.

7 Dec 2018 | Technical Committee Meeting

The Technical Committee (TC) meeting held last 7 December 2018 at Heritage Manila Hotel was attended by various stakeholders of the project.